Team Elmer's has constructed waste water treatment facilities throughout the state of Michigan.

Our Process

  • Prepare subgrade
  • Deploy PVC liner
  • Install cover layer in sand
  • Install topsoil or stone side slopes (if required)
     

Certifications

  • Confined Space
  • H2S Gas Certified
  • Electrofusion, Butt Fusion, and Extrusion Welding
  • Hazwhopper certified
  • Fresh Air Make-Up Systems (Portable and Stationary)
  • Methane awareness training
  • Gas Monitoring Devices
 


Related Services

  • Ductile iron pipe installation
  • Influent and effluent piping installation,
  • Sprinkler system installation
     

GPS

Team Elmer's also employs GPS (Global Positioning System) into our waste water construction projects. The GCS900 (Grade Control System 3D Automatic Control) from Trimble puts design surfaces, grades and alignments inside the cab. You can operate the system in a completely stakeless environment and grade to an accuracy of 0.1 ft.

Bottom line: GPS takes what the engineers and surveyors see on a computer screen and turns it into a hands-on product out in the real world.

How It Works:

1) A design surface is built in AutoCADD from construction plans and is uploaded to the GCS900.

2) We perform a site-calibration on-site. A site-calibration converts the design surface coordinates to GPS coordinates which allows the D6T to know its location relative to the site.

3) The dozer operator can then drive anywhere on-site and know the precise cut or fill to finished grade. The blade of the dozer is controlled by the GPS unit and will follow the design surface.

4) The package also included a Rover unit which can be used on-site separate from the Dozer to check grades, calculate volume of materials, and supply survey stakes.